Shop 'n Save
Crossings at Halls Ferry
Ferguson, Missouri


Jobs Site Photo at Time of Report Demolition work, existing Central Hardware building down, work on roof and interior of adjacent building to Shop 'n Save. Setting angle for new stud partition. Roof opened for demolition, work on RTUs for removal.
October 4, 1997

Jobs Site Photo at Time of Report Water line relocation and new meter being set.
October 17, 1997

Jobs Site Photo at Time of Report Jobs Site Photo at Time of Report
November 4, 1997
Demolition of the Mark I and adjoing building is underway the existing Shop 'n Save wall has been secured and the sprinkler system reconnected to the new main. Grading and fill has benn underway on the eastern quarter of the building.

Jobs Site Photo at Time of Report Foundation work is complete and masonry is underway. Plumbing is working on underfloor systems. Backfilling in progress where conditions permit. Final pad compaction verification in dock area.
January 9, 1998

Jobs Site Photo at Time of Report Jobs Site Photo at Time of Report
Feburary 3, 1998
Preparation of roof blocking and deck completion in preparation for roof to begin. Light guage framing of facade and canopy. Interior plumbing and electric underway in preparation for slab pour.

Jobs Site Photo at Time of Report Final slab pour underway today. Ligh guage framing and drywall sheathing of front facade. Plumbing rough-in. Electrical rough-in. Mechanical starting ductwork hanging.
Feburary 19, 1998

Jobs Site Photo at Time of Report Exterior loading dock slab. Final exterior drywall on EIFS soffits and fascia. Board up and security. Interior work underway: - Steel stud partition layout. - Electric rough-in and temp. lighting. - HVAC ductwork. - Sprinkler mains.
Feburary 26, 1998

Jobs Site Photo at Time of Report RTU and mechanical house delivery and placed. All trades underway in store. Electric main panels installed and distribution. Plumbing and refrigeration underway. HVAC ductwork on job and installation in progress.
March 5, 1998

Jobs Site Photo at Time of Report All trades underway in store, stud and drywall work underway. Electric main panels installed and distribution. Mechanical and refrigeration underway. Electrical underway.
March 12, 1998

Jobs Site Photo at Time of Report Exterior EIFS base started. Storefront and automatic door instalation started. All trades underway on sales floor.
March 26, 1998

Jobs Site Photo at Time of Report All trades underway on sales floor. Drywall near complete in sales area. Mechanical completed ductwork. Ceiling geid complete in sales area. Electric hanging light fixtures in sales area. Floor tile is 70% complete on sales floor. Exterior EIFS near complete. Storefront and glazing near complete.
April 2, 1998

Jobs Site Photo at Time of Report Exterior EIFS being completed. Site grading and testing preparation for paving. Balance of lights, electric and mechanical above ceiling to drop ceiling tiles. 1st equipment deliveries, cases set.
April 24, 1998

Jobs Site Photo at Time of Report Parking lot paving has been started. Exterior cleaning and flashing installations underway. Interior finish and decor installations. Refrigeration and electrical equipment installations.
May 1, 1998

Jobs Site Photo at Time of Report Equipment, shelving and decor underway. Refrigeration underway.
May 7, 1998

Jobs Site Photo at Time of Report Electric is being completed, lights and all refrigeration equipment. Store decor is being completed. Stocking of store is underway. Rear paving was completed this week.
May 30, 1998

Jobs Site Photo at Time of Report Jobs Site Photo at Time of Report
June 19, 1998
Final fixturing and stock going into store. Exterior painting, signs and final clean-up for opening.